Manifold Recovery

Client: Boskalis Subsea

Project: Neptune Juliet Manifold Recovery Engineering

Scope: Recovery analysis, rigging redesign, seafastening redesign and offshore installation support

Vessel: CSV Ocean Yield Connector

Project Overview

Elgenio provided recovery engineering support for the Neptune Juliet manifold, including dynamic lift analysis, rigging redesign and development of a simplified seafastening arrangement for recovery to the deck of the CSV Ocean Yield Connector.

The scope was undertaken late in the project following a change within the project engineering team, with the objective of reviewing the existing recovery arrangements and identifying opportunities to simplify fabrication, installation and rigging.

The Challenge

The existing recovery concept used a substantial fabricated support frame beneath the manifold to transfer loads into the vessel deck.

While structurally workable, the arrangement introduced a significant amount of fabricated steelwork and additional installation effort on the vessel.

The project also relied on a more complex rigging arrangement using specialist Dyneema slings, increasing both procurement cost and lead time.

With the recovery campaign approaching, the revised project team required a simpler solution that could be engineered and delivered within a tight programme while maintaining the required structural and lifting performance.

Engineering Scope

  • OrcaFlex Recovery Analysis
  • Rigging Redesign
  • Off-the-Shelf Sling Selection
  • Seafastening Redesign
  • Shear Stop Design
  • Deck Interface Review
  • General Cargo Seafastening
  • Rigging Technical Documentation

The Solution

Elgenio reviewed the existing recovery arrangement and developed a much simpler seafastening concept based on using the manifold's own mudmats as the primary bearing points on the vessel deck.

This removed the need for the large fabricated support frame. Horizontal restraint was instead provided using simple local deck-mounted cleats and shear stops.

The revised arrangement substantially reduced fabricated steelwork, simplified vessel integration and reduced the amount of installation work required during mobilisation.

The recovery analysis was also re-developed in OrcaFlex to confirm the governing lifting loads and dynamic response of the manifold during recovery.

The rigging arrangement was redesigned around readily available conventional slings, removing the requirement for specialist Dyneema components and reducing both procurement cost and lead time.

Results

Simplified Seafastening

The large fabricated support frame was eliminated by using the manifold mudmats directly on deck with local cleats and shear stops.

Reduced Fabrication & Installation

The revised concept substantially reduced steelwork, fabrication effort and mobilisation requirements.

Lower Rigging Cost & Lead Time

The rigging was redesigned around conventional off-the-shelf slings, avoiding specialist components and shortening procurement lead time.

Need a more practical solution for an offshore recovery or seafastening scope?

Elgenio can review existing concepts and develop simplified engineering solutions that reduce fabrication, rigging and offshore execution requirements.