Umbilical Installation

Client: North Sea Operator

Project: Umbilical Installation

Scope: Pull-in engineering, installation analysis, equipment design, point cloud integration, seafastening, draughting and technical animation

Project Overview

Elgenio provided engineering support for the installation of a new electro-hydraulic umbilical between a North Sea platform and nearby subsea manifold.

The umbilical was required to be pulled through an existing J-tube, with the topside J-tube opening and hang-off location positioned within a congested area of the platform with restricted head height and sensitive existing pipework.

The scope developed from early concept screening through pull-in analysis, equipment design, installation analysis, seafastening, draughting and technical visualisation.

The Challenge

The topside pull-in arrangement was located within a highly congested area of an ageing offshore asset, where limited original information was available and existing pipework had to remain protected throughout the installation.

Restricted head height above the J-tube limited the available overpull arrangement and reduced the space available for conventional pull-in equipment.

The engineering solution therefore had to minimise modifications to the platform while providing a compact arrangement capable of safely transferring the required pull-in loads.

Engineering Scope

  • Concept & Pull-In Option Screening
  • Site Survey & Interface Review
  • Pull-In Analysis
  • Winch & Equipment Load Definition
  • Winch Pull-In System Design
  • Sheave Frame Design
  • Installation Sequence Development
  • Umbilical Installation Analysis
  • Lay Spread Seafastening Design
  • Point Cloud Integration
  • Project Draughting Support
  • Technical Animation

The Solution

Point cloud data was incorporated into the design process to review the existing platform geometry, identify potential clashes and screen pull-in arrangements before the site visit.

This allowed the site visit to focus on the most practical options and helped minimise the amount of offshore survey work required.

Pull-in analysis was then used to establish the required winch loads and support accurate specification of the topside equipment.

The winch and pull-in system were designed to be as compact as practical so the equipment could be transported offshore and assembled in situ. Bolted connections were used throughout the system to reduce individual component size and simplify offshore handling and load testing.

The resulting pull-in arrangement provided the engineering basis for the wider umbilical installation campaign, including the associated lay spread, seafastening and installation analysis.

Results

Compact Pull-In Solution

A compact topside pull-in arrangement was developed around the restricted available space and existing platform infrastructure.

Integrated Design Development

Point cloud data, pull-in analysis and equipment design were combined to develop the arrangement around the real platform interfaces.

Installation Campaign Support

The engineered pull-in system provided the basis for progression of the wider umbilical installation campaign.

Download case study A printable PDF summary of this project is also available. Download PDF

Need engineering support for a complex cable or umbilical installation?

Elgenio can support pull-in engineering, installation analysis, equipment design and offshore preparation from concept through project execution.