Decommissioning Feed

Client: Maersk Supply Services

Project: MSS Dunlin Alpha Conductor Guide Decommissioning FEED

A FEED study into the removal of the 200Te & 400Te Dunlin Alpha conductor guide frames and conductor as part of the Dunlin Alpha decommissioning program.

Services provided as part of this scope:

  • Weight Take off lifted components
  • Structural Analysis of the CGF frames during cutting
  • Structural Analysis of the CGF frames for lifting
  • CGF Rigging Specification
  • Conductor free standing check
  • Shear Pin for Conductor Lift Check